Zuluf Oilfield Water Treatment Plant Operations
Operations began at the new groundwater treatment plant for the offshore Zuluf oilfield with first usable water on July 1, 2026.
corporate_fare
Client
Saudi Aramco
construction
Contractor
Fisia Italimpianti (Webuild Group)
location_on
Location
Zuluf Field / Tanajib Industrial Hub
schedule
Timeline
First Water Produced July 1, 2026
payments
Est. Value
$330 Million Facility
description Project Overview
Fisia Italimpianti (Webuild Group) commenced full commercial operations at the newly built water treatment plant for the offshore Zuluf oilfield. The facility purifies deep aquifer saline water to provide 185,000 m³/day of treated water for offshore reservoir pressure reinjection.
engineering Technical Specifications
check_circle
capacity
185,000 m³/day
check_circle
first water
July 1, 2026
check_circle
contractor
Fisia Italimpianti (Webuild)
check_circle
client
Saudi Aramco
satellite_alt Survey & Geomatics Relevance
Projects of this scale and category typically require comprehensive surveying disciplines including:
- chevron_right Multibeam Swath Bathymetry (IHO S-44 Order 1a)
- chevron_right Sub-Bottom Profiling & Seabed Geophysics
- chevron_right Pipeline Route Surveys & As-Built Verification
- chevron_right ROV-Assisted Structural Inspection
- chevron_right Metocean & Tidal Station Monitoring
Project At a Glance
corporate_fare
Client
Saudi Aramco
construction
Contractor
Fisia Italimpianti (Webuild Group)
location_on
Location
Zuluf Field / Tanajib Industrial Hub
schedule
Timeline
First Water Produced July 1, 2026
domain
Category
Offshore Intelligence - July 2026
payments
Value Estimate
$330 Million Facility
Project Status
Active Operations